Global perspective. Clear attribution. Updated throughout the day.
Live desk Concise briefs from trusted publishers · Always follow the source for the full report
Markets
GBP/USD 1.3256 FrankfurterEUR/USD 1.1399 FrankfurterUSD/NGN 1,327.99 FrankfurterUSD/JPY 158.32 FrankfurterGold $4,286.20/oz Gold APISilver $64.42/oz Gold API
Breaking
Nigeria Open golf tournament set for return in November 2027 Punch NigeriaObi urges editors to examine politicians’ records before elections Punch NigeriaYobe deputy governor praises peaceful conduct of local council election Punch NigeriaAccord candidate projects more than one million Osun votes for Tinubu in 2027 Punch NigeriaEkiti PDP figure backs Oyebanji-led effort for Tinubu in 2027 Punch NigeriaLow turnout marks Enugu local government election as voters cite apathy Punch NigeriaIreland squad votes to proceed with Israel Nations League fixture Punch NigeriaDelta NDC candidate rejects Urhobo endorsement of Oborevwori Punch NigeriaBJP says election panel note has settled dispute as Congress seeks answers NDTVKerala minister says inhabited areas will be excluded from ESA notification The Hindu
Scores
Ukraine U21 v Turkey U21 15:00 UTC UEFA European Under-21 Championship · TheSportsDBCroatia U21 v Hungary U21 1–0 UEFA European Under-21 Championship · TheSportsDBLatvia U21 v Germany U21 15:00 UTC UEFA European Under-21 Championship · TheSportsDB
Business

Bridge linking Kottayam and Alappuzha districts targeted for mid-October opening

Source: The Hindu · 26 Sep 2026, 14:40 UTC
Bridge linking Kottayam and Alappuzha districts targeted for mid-October opening
Image: The Hindu · original report

The completed Nerekadavu-Makkekadavu bridge across Vembanad Lake is expected to open by mid-October, officials say, after approach-road and electrical works are finished. The ₹93.35 crore project began in 2016 but was delayed by land acquisition and a later revision of its estimate.

The Nerekadavu-Makkekadavu bridge linking Kerala’s Kottayam and Alappuzha districts is expected to open to traffic by mid-October, officials said on Saturday. The 800-metre bridge across Vembanad Lake connects Udayanapuram grama panchayat in Kottayam with Thaikkattussery panchayat in Alappuzha. Construction of the bridge has been completed, while work continues on approach roads and retaining walls.

Water Resources Minister Mons Joseph reviewed the project and said arrangements had been finalised for the Kerala State Electricity Board to lay electrical cables. He instructed the board to complete the work within five days, after which tarring of the approach roads would begin. The original target was to finish all works by September 30, but the minister said additional time would be needed.

The Irrigation department is also studying the section of approach road running beside a canal. An estimate will be prepared and additional funds allocated based on the study. Joseph directed officials to take immediate steps to develop the road connecting the Vaikom-Ernakulam road with the bridge.

Vaikom MLA K. Binimon said efforts were under way to open the structure by mid-October. The bridge was built at a cost of ₹93.35 crore under the second phase of the Thuravoor-Pampa road project.

It is 11.23 metres wide and has 22 spans. Officials expect it to shorten the route between Thuravoor in Alappuzha and Vaikom in Kottayam and improve connectivity to Kochi. Work began in 2016 with an 18-month completion target.

The project was later stalled by delays in acquiring land for the approach roads. Land acquisition was completed in 2022 after a Kerala High Court directive, while the contractor subsequently sought a revised estimate because of cost increases. The revised estimate was approved last year.