Global perspective. Clear attribution. Updated throughout the day.
Live desk Concise briefs from trusted publishers · Always follow the source for the full report
Markets
GBP/USD 1.3235 FrankfurterEUR/USD 1.1287 FrankfurterUSD/NGN 1,329.04 FrankfurterUSD/JPY 157.90 FrankfurterGold $4,141.80/oz Gold APISilver $60.52/oz Gold API
Breaking
Ogun ADC urges members to settle disputes internally Punch NigeriaKatsina begins disbursement of women’s community investment funds Punch NigeriaSecurity forces pursue rescue of 19 abducted corps members in Imo Punch NigeriaKebbi teachers praised for staying in classrooms despite economic strain Punch NigeriaNANS urges Ogun to upgrade Gateway institute to polytechnic Punch NigeriaIndian judge warns mass voter deletions would breach constitutional principles India TodayOsun asks court to lift order restricting state accounts Punch NigeriaFormer Bastar security camp converted into hostel for tribal students The HinduDelhi police detain nearly 500 as protests over election chief continue The HinduInvestigation into Anthony Kila’s professorial title prompts calls for wider scrutiny Premium Times
Scores
Colorado Springs Switchbacks v Oakland Roots 0–0 American USL Championship · TheSportsDBFC Tulsa v Sacramento Republic 1–1 American USL Championship · TheSportsDBLas Vegas Lights v San Antonio 1–0 American USL Championship · TheSportsDB
Science & Health

SLBC tunnel project passes collapse zone as excavation accelerates

Source: The Hindu · 04 Oct 2026, 15:31 UTC
SLBC tunnel project passes collapse zone as excavation accelerates
Image: The Hindu · original report

Excavation on Telangana’s SLBC tunnel has moved beyond the geological zone where eight workers died in a collapse, according to Irrigation Minister N. Uttam Kumar Reddy. Officials say more than 700 metres have been excavated since work restarted, with completion and water delivery targeted for 2028.

Work on Telangana’s Srisailam Left Bank Canal tunnel has moved beyond the difficult geological stretch where a collapse killed eight engineers, technicians and workers in February last year, Irrigation Minister N. Uttam Kumar Reddy said on Sunday. The minister said the progress would allow additional equipment to be deployed and improve operational efficiency, while safety measures remained in place.

He reviewed the project with engineers, contractors, elected representatives and other agencies in Hyderabad. Reddy said more than 700 metres had been excavated since work restarted in February. About 450 metres had been completed from the Devarakonda outlet and 250 metres from the Srisailam inlet.

The 43.968-kilometre main tunnel was described as nearly 79% complete, with about 9.1 kilometres still to be excavated. The government is targeting completion by June 2028 and water delivery within that timetable. Army tunnel expert Col.

Parikshit Mehra said work from the inlet had initially been slowed because of weak ground, rock bursts and the need to reduce risks. The team diverted around the point where a tunnel-boring machine had become stuck and worked through unstable conditions. The engineers installed 140-millimetre seamless pipes to create an umbrella canopy ahead of excavation.

Reinforced ribs, staged excavation, probe drilling and additional supports were also used, according to the project briefing. The minister said the removal of excavated material over distances of up to 21 kilometres remained a major constraint. When hauling fell behind, material accumulated inside the tunnel and forced work at the excavation face to stop until the backlog was cleared.

Officials said additional drilling equipment and a German locomotive were being deployed. Breakthrough in Tunnel 1 could occur in May or June 2028, while sprayed lining continued. Lining work on the 7.1-kilometre Tunnel 2 had also resumed after a prolonged interruption.